Hokitika Racecourse Development

The enabling Infrastructure project at the old Hokitika Racecourse is nearing completion. The wastewater, stormwater and drinking water projects have all been completed and connected into existing infrastructure. The Park Street extension is 90% complete, and the final seal on the road will be completed during October. Work is currently underway linking the new road extension into Park Street.

Ross Pool Strengthening

The Ross pool structural and architectural designs have been submitted for building consent. As soon as the consent is granted, the structural repair & strengthening project will start



High levels walkway access – Milltown Weirs West Coast Cycle Trail

The concrete bridge pylons at Milltown Weirs have been successfully poured and cured for the two high-water walkways. These structures are now in place. The installation of the walkways is completed, We have started with the ramps that will connect the walkways to the trail. Just need to receive signs and install, then completed.