Hokitika Racecourse Infrastructure development
The enabling infrastructure project at the Hokitika Racecourse is progressing on programme and on budget. The stormwater installation is nearing completion with the trenching virtually completed, many manhole connections completed and almost half of the sump connections completed by the beginning of May.
The wastewater trenching is also close to completion, although there is still some way to go to complete the wastewater manhole connections.
In early May the construction team was focused on installing the last two pressure manholes for the stormwater and connecting into the town belt east stormwater line, and this is nearing completion.
Work has also started on the new Park Street road extension with compaction and levelling.
The project is currently on track to be completed by end of September 2025.